OVERVIEW

ENERGY EFFICIENCY

OTHER SUSTAINABILITY FEATURES & MEASURES

DRAWINGS

MORE CASE STUDIES

ABOUT THE 2030 CHALLENGE

 
   
 

Building Type:
Office

Owner:
Rolf C. Hagen Inc.
www.hagen.com

Location:
Baie d'Urfé, Quebec

Budget: $8,649,788

Completion: Summer 2006

PROJECT TEAM

Architect:

Rubin & Rotman Associates

Client representative:

Dahltan Entreprises Inc.

Landscape architect:

Beaupré et associés Experts conseils

Civil engineer:

Groupe Teknika (now EXP)

Structural engineer:

BCA Consultants

Mech./elec. engineer:

PMA et associés

Commissioning:

Martin Roy et associés

General contractor:

Broccolini Construction Inc.

Mech. contractor:

Kolostat

Hagen Head Office

Rubin & Rotman associates

OTHER SUSTAINABILITY FEATURES & MEASURES


Products & Materials

PHOTO at right: Stéphane Brügger

The following materials contribute to the building’s lifecycle sustainability:

  • Open grid ceiling along the perimeter of the building enables the slabs to radiate both up and down.
  • Low R-value carpeting does not interfere with performance of the radiant slabs.
  • The paints, varnishes, sealants and glues used on the work site emit little or no VOCs.

Building materials with recycled content include:

  • Steel structure;
  • Cast concrete elements (partial replacement of cement by fly ash);
  • Recycled content gypsum panels and suspended ceiling tiles;
  • 100% recycled material carpet backing.

Regional products include:

  • River pebbles used in the outdoor design;
  • cast concrete;
  • limestone;
  • concrete blocks;
  • gypsum panels;
  • locally manufactured prefabricated concrete panels.

Mature trees felled in preconstruction work – including maples, oaks, lindens and ash – were recovered, dried, cut into planks and turned into soffits, wall panels, furniture components and interior decoration.



Water Conservation

Outside:

  • Much of the original vegetation was conserved, and all landscaping was based on indigenous plants that can resist dry spells, eliminating the need for a automated irrigation system.
  • During construction, shallow ditches were dug at the perimeter of the construction zone. These ditches gathered potentially contaminated runoff water and moved it by gravity to a sedimentation pit. Some sediment was filtered by rock fill before entering the pit, and the rest accumulated at the bottom of the pit through a bi-level system of drains. Clean surface water was returned to the water table through the stream.
  • A variation on this system is part of the final water conservation strategy: the paved surfaces of parking areas and traffic lanes drain toward the ditches at the perimeter. Overall, this practice ensures that the water table is fed almost to the pre-development level, and it reduces loading of the storm sewer infrastructure.

Inside:

  • Controlled-flow faucets, double-flush toilets with infrared detectors, and dry urinals reduce water consumption.