OVERVIEW

ENERGY EFFICIENCY

OTHER SUSTAINABILITY FEATURES & MEASURES

DRAWINGS

MORE CASE STUDIES

ABOUT THE 2030 CHALLENGE

 
   
 

Building Type:
Office

Owner:
Manitoba Hydro

Location:
360 Portage Avenue, Winnipeg, Manitoba

Budget: $278,000,000
(total project cost)
65,000m² (700,000 ft²)

Completion:
September 2009

PROJECT TEAM

Design Architect:

Kuwabara Payne McKenna Blumberg Architects

Associate Architect:

Smith Carter Architects and Engineers

Advocate Architect:

Prairie Architects

Energy/Climate Engineers:

Transsolar Energietechnik

General Contractor:

J.D. Strachan Construction Ltd

Landscape Architect:

Hilderman Thomas Frank Cram

Phillips Farevaag Smallenberg

Civil Engineer:

MTE

Mechanical/Electrical Engineer:

AECOM (formerly Earth Tech)

Structural Engineer:

Crosier Kilgour & Partners Ltd.

Halcrow Yolles

Interior Design - Base Building/Public Space:

KPMB Architects

Interior Design - Office:

IBI Group

Number Ten Architectural Group

Environmental Space Planning

Commissioning Agent:

Enermodal

Owner/Developer:

Manitoba Hydro

Building Envelope Consultant:

Brook Van Dalen & Associate

Lighting Design:

Pivotal Lighting Design

Microclimate:

RWDI Inc

Geothermal:

Groundsolar Energy Technologies

Omicron Consulting Group

Life Safety:

Leber | Rubes

Vertical Transportation:

Soberman Engineering

Acoustics:

Aercoustics Engineering Ltd.

Quantity Surveyor:

Hanscomb

Municipal & Site Services:

Wardrop Engineering

Traffic/Access/Parking Engineer:

ND Lea Engineers & Planners

Geotechnical Engineer/
Hydrogeologist:

UMA Engineering

Geotechnical Engineer:

Dyregrov consultants

Water Feature Consultant:

Dan Euser Water Architecture

Manitoba Hydro Place

Kuwabara Payne McKenna Blumberg Architects
Smith Carter Architects and Engineers
Prairie Architects

OTHER SUSTAINABILITY FEATURES & MEASURES


Products & Materials

PHOTO: Gerry Kopelow
  • Durability, life cycle costs, regional relevance and health and well-being were critical factors in developing the building’s material palette. Large portions of the structure were left exposed to increase the conductivity of the radiant concrete mass, and to reinforce the open ‘loft’ concept. Color is used as an organizing element throughout the office spaces: the building core is painted red, and runs the full height of the building.
  • Locally quarried Tyndall limestone and regionally sourced granites reinforce Winnipeg’s fabric of masonry buildings and Manitoba Hydro’s relationship to the northern landscape. The embodied energy of all materials was considered before selection.
  • Douglas Fir elements, mostly reclaimed from the buildings previously occupying the site, are applied in key public spaces to introduce warmth and texture.
  • All carpet tile is made from 100% recycled materials.
  • All interior materials meet Low VOC standards.
  • The towers’ exteriors are composed of high-performance double and triple glazed unitized curtain wall panels. Curtain wall components were assembled locally to minimize costs, to facilitate quick and proficient installation and to minimize delays due to the extreme climate.

 

Other Features & Measures

PHOTO: Gerry Kopelow

Manitoba Hydro Place occupies a previously underutilized site formerly occupied by several vacant buildings and designated a Brownfield. Soil remediation was required to remove patches of hydrocarbon contaminants, and the vacant buildings were carefully deconstructed so that 95% of the components could be recycled or reused. For example, old growth Douglas Fir beams were milled and reused in the new building for soffits and benches.

The two towers of the building sit on a street-scaled podium. Structural and glazing systems emphasize lightness and transparency to reduce the impact of the mass on the surrounding neighborhood. Large-scale entrance canopies protect from prevailing winds and provide shelter for pedestrians.

Green roofs cover the podium roof, a dramatic increase in soft landscaping compared to the hard surface parking lots and tar roofs of the original site. All of the green roofs are planted with native plant species and one of the green roofs is dedicated to the First Nations and was planted with sweetgrass in a traditional ceremony. An increased number of street trees and a grove at the site’s south park help create shade conditions at grade.

Sixty-five percent of the population of the building travels to work by transit, 5% by bike or foot and 3 % via carpool. There are only 151 parking spaces for 2100 occupants and visitors.

The project utilized an Integrated Design Process (IDP), as outlined by the Canadian Government’s National Research Council as IDP-2000, to design and develop ideas. Fifteen initial schemes were created, then three were short-listing for further development. The measures of potential success for each design were based on criteria important to the client and the goal of reaching specified energy targets and urban renewal gestures. Ongoing charrettes after the final project selection coalesced the preliminary strategies into real systems. The highly integrated nature of some of the elements, such as atrium water features and the buildings humidification/de-humidification facilities are a direct outcome of immediate collective intelligence at these charrettes. By merging traditional proven techniques with metered and controlled building components, energy savings potential and design quality were met and exceeded throughout the building. Furthermore, the commissioning process of the project involved ongoing input from key consultants through monthly meetings and a distance monitoring program with the BMS. All of the visible systems were scrutinized, tested, modified and refined by every specialist on the team (including the architects) to ensure every element was synchronized to the whole and harmonized in proportion, form, and scale.

Water Conservation

PHOTO: Eduard Hueber

Deep-soil intensive green roofs on roof of podium create accessible terraces as an outdoor amenity for employees, while also reducing storm-water runoff and providing additional thermal insulation.

Excess rainwater is held within the green roof tray system until the planting medium is ready to absorb it. In addition, excess condensate generated by the building’s fan coil units during the hot summer months is directed to large cisterns located in the building’s parking garage. When conditions warrant, this reclaimed water is pumped back up to the green roof and redistributed via a drip irrigation system.

Waterless urinals and low-flow toilets and sinks are used throughout the building.

Precipitation managed on site: 100% of precipitation that lands on podium/tower is directed to irrigation tank

  • Total water used indoors: 8,687,952 l/yr (from LEED submission)
  • Total water used outdoors: Natural precipitation. During low precipitation condensate from the fan coils is used for irrigation (as the system is hands-off quantities have not been measured)
  • Percentage of total water from reclaimed sources: 100% of water used outdoors
  • Percent wastewater re-used on-site: 0%
  • Calculated annual potable water use: 134 l/m²a